Closures expected this month on Doniphan Drive for Border West Expressway Project

These closures along Doniphan Drive are set to last through June 15. (Credit: MGN Online)

Beginning Friday, El Paso Electric crews will start working on transmission lines for the Border West Expressway Project.

The work will be done between Doniphan Drive and the Buena Vista subdivision at Racetrack Drive.

The northbound right-hand lane on Doniphan Drive and a section of Vista Hill Drive will be closed in order to complete the work.

The closures will take place on the following days:

  • 8 p.m. to 10 p.m. June 2
  • 6 a.m. to 8:30 p.m. June 3
  • 6 a.m. June 4 to 6 a.m. June 5
  • 8 p.m. to 10 a.m. the following morning from June 5 to June 8
  • 8 p.m. to 10 p.m. June 9
  • 6 a.m. to 8:30 p.m. June 10
  • 6 a.m. June 11 to 6 a.m. June 12
  • 8 p.m. to 10 a.m. the following morning from June 12 to June 15